UPDATE: Hydro-Québec will soon begin major work to upgrade the underground electrical network on Sabin and Redwood avenues, as well as on Holland and Weizmann roads. This work is intended to improve service quality and increase network capacity to meet growing demand.
| Street | Duration | Start | End |
| Redwood Avenue | 46 | May 20, 2025 | August 7, 2025 |
| Weizmann Road | 30 | May 20, 2025 | July 2, 2025 |
| Sabin Avenue | 53 | June 2, 2025 | August 28, 2025 |
| Holland Road | 28 | June 4, 2025 | July 15, 2025 |
- Work schedule: Monday to Friday, 7 a.m. to 6 p.m.
- Work details: Replacement of underground conduits and vaults, lighting work, street paving, and sidewalk reconstruction.
- No power outages are planned.
- Access and traffic: Roads will be closed to through traffic, but local access will be maintained. Detours will be in place.
- If private driveways are affected, residents will be notified 3 days in advance.
- Waste collection services will not be interrupted.
- Hydro-Québec will restore all work areas to their original condition after completion.
For more information, contact Hydro-Québec at 1-866-388-1978 or [email protected].
In case of an electrical outage or emergency, call 1-800-790-2424 at any time.