- Aqueduct repair (sleeving) timeline
Rosedale between Merton and Baily: June 12 to July 14
Phase | Timeline |
---|
Excavation | June 12—15 |
Sleeving | June 15—28 |
Paving | July 7—14 |
Côte Saint-Luc Road between Robinson and Prince of Wales: June 26 to July 28
Phase | Timeline |
---|
Excavation | June 26 — 28 |
Sleeving | June 28 to July 12 |
Paving | July 24 — 28 |
Sunnybrooke between Westover and Côte Saint-Luc Rd: June 27 to Aug. 11
Phase | Timeline |
---|
Excavation | June 29 – July 5 |
Sleeving | July 17 — 21 |
Paving | Aug. 7 — 11 |
Guelph between McMurry and Melling: July 3 to Aug. 29
Phase | Timeline |
---|
Excavation | July 13 — 20 |
Sleeving | July 24 — 28 |
Paving | Aug. 21 — 29 |
Trudeau Park: July 20 to Sept. 15
Phase | Timeline |
---|
Excavation | July 20 —26 |
Sleeving | Aug. 15—September 1 |
Paving | Sept. 11 — 15 |