Major Infrastructure Projects: 2023 Timeline

Major infrastructure projects have started in Côte Saint-Luc. This works includes adding wider sidewalks, replacing the city section of lead water services line, replacing other old infrastructure, new signage and street marking with long duration street paint.

Follow the evolution of the work and to know how it impacts traffic. 

Sir Winston Churchill / July 10 – Oct. 9

PhaseTimeline
Preparatory work July 10 – 11
Hydro-Québec workJuly 10 – Aug. 25
Lead pipe replacementAug. 28 – Sept. 1
Sidewalk and road demolition and reconstructionSept. 5 – 20
PavingSept. 26 – 27
Repairing of entrances (pavé-uni, grass)Sept. 27 – 29
Street paintingOct. 9

Hartwell / July 10 – Sept. 22

PhaseTimeline
Preparatory work July 10 – 11
Hydro-Québec workJuly 10 – Aug. 25
Lead pipe replacementAug. 23 – Sept. 14 
Sidewalk and road demolition and reconstructionSept. 5 – 20
PavingSept. 18 – 19
Repairing of entrances (pavé-uni, grass)Sept. 20 – 21 
Street paintingSept. 22

Fleet (eastbound from Cavendish to Alpine) / July 21 – Aug. 29

PhaseTimeline
Preparatory work July 21
Sewer system repairsJuly 24-25
Sidewalk demolition and reconstruction
July 25 – Aug. 4
Road demolition and reconstruction
Closure of Fleet eastbound – Detours through Merton and Baily – One lane of Fleet westbound will be taken for an exit path
Aug. 7 – 11
Paving
Repairing of entrances (pavé-uni, grass)
Street painting
Completed

Cavendish overpass (southbound) / July 17 – Aug. 17

PhaseTimeline
Preparatory work July 17
Sewer system repairsJuly 18-19
Sidewalk demolition and reconstructionJuly 24 – Aug. 7 
Road demolition and reconstruction
Closure of Cavendish Overpass – Detour to Kildare
Aug. 7 – 11
PavingAug. 11-15 
Repairing of entrances (pavé-uni, grass)Aug. 16
Street paintingAug. 17
Completed

Parkhaven (between Wavell and Chamberland) / July 17 – Sept. 5

PhaseTimeline
Preparatory work July 17
Sewer system repairsJuly 18-19
Lead pipe replacementJuly 20-28
Sidewalk demolition and reconstruction
Complete road closure – Minor detour
Aug. 7 – 11
Road demolition and reconstructionAug. 14 – 28
PavingAug. 29 – 30
Repairing of entrances (pavé-uni, grass)Aug. 31 – Sept. 1 
Street paintingSept. 5
Completed

Cavendish Boul. (southbound from Kildare to Heywood) / July 21 – Aug. 24 

PhaseTimeline
Preparatory work July 21
Sidewalk demolition and reconstructionJuly 24 – Aug. 7
Road demolition and reconstruction
Repaving Kildare/Cavendish east half intersection – Closure of Cavendish Northbound at Heywood – Detour through Cavendish overpass
Aug. 7 – 11
PavingAug. 15-18
Repairing of entrances (pavé-uni, grass)Aug. 23 
Street paintingAug. 24
Completed

Merton (between Lyndale and Glencrest) / Aug. 7 – Sept. 11 

PhaseTimeline
Preparatory work Aug. 7
Road demolition and reconstruction
Complete road closure – Minor detour
Aug. 7 – Aug. 15
Sewer system repairsAug. 8 – 14 
Lead pipe replacementAug. 15 – 18
Sidewalk demotion and reconstruction Aug. 21 – 25
Paving Sept. 6 
Repairing of entrances (pavé-uni, grass)Sept. 7
Street paintingSept. 11 
Completed