1. Announcements
  2. /
  3. Road work
  4. /
  5. Lane closures on Clanranald,...

Lane closures on Clanranald, intersection with Vézina (4 weeks)

Traffic and parking

  • Phase 1 – Avenue Clanranald: Closure of southbound lane at Rue Vézina intersection. Flaggers will be present to assist traffic flow in both directions
  • Phase 2 – Avenue Clanranald: closure of northbound lane at Rue Vézina intersection. Flaggers will be present to assist traffic flow in both directions
  • On-street parking not available during the project
  • To ensure safety and optimize traffic flow during construction, please obey traffic signs (detours, local traffic, etc.).

Estimated duration:

  • 4 weeks starting the week of May 21 (approximately May 21 to June 18)
  • Hours: Monday to Friday, 7 a.m. to 7 p.m

Reason: Optimization of the waterworks system by the City of Montréal –Upgrading a valve and a measurement chamber